Steps Towards a Record of Site Condition (RSC) – The Submission Process

Concluding this past month’s theme of the RSC submission process we will be concluding (logically) with the submission of the RSC. To start, an RSC is a document submitted to the Ontario Ministry of the Environment describing the environmental conditions at a site. Included in the RSC is such information as the site owner, the assessor, the size of the property, the concentrations of chemical species on the site at the time of reporting and the scope of any remedial activities that occurred at the site. The RSC stands as a snapshot of the site conditions and documents that the property is in agreement with applicable standards, this could be important in the future if…

i) More stringent regulatory standards are adopted for a chemical found on a property. In this instance the RSC indemnifies the owner from having the responsibility of having to bring site within the new standards as the RSC shows that the owner has already performed the necessary due diligence at the site.

ii)The property is sold and then an environmental incident occurs on the property. With the RSC it is easy refer to the historical condition of the property for baseline information.

iii)The land use is going to be changed from a less restrictive to a more restrictive use (eg. Industrial to residential)

Regardless of why the RSC is being submitted it requires a Qualified Person (QP) as defined by the Ontario Brownfields Regulation in the completion and submission of the required documentation. As the act defines it, a qualified person is a Professional Engineer (P.Eng.) or Professional Geologist (P.Geo.) who is certified to practice in Ontario and has registered themselves as a QP (Please note, just because a consultant is a P.Eng. or P.Geo is does not necessarily mean that they are a QP, as they may not have registered themselves as a QP).

An RSC can be submitted by a QP at any time in the investigation after an appropriate Phase I ESA has been completed. That being said, an RSC will only be accepted and filed by the MOE once all potential environmental concerns regarding the site have been determined, studied and if present, quantified and addressed (eg. Remediated). So there is no point in attempting to submit an RSC for a property after a Phase I ESA if the historical searches showed that a gas station was next door in the 1950’s. Also, there is no point to try and file an RSC for the same property after you've tested the soil and found PHC to be above regulatory limits, in fact, you won’t even be able to submit the RSC because the on-line submission process will reject your submission if any of the chemical concentrations your enter are above criteria. Also, if the land use of the property is going to be changed to a more restrictive one, then any chemical results for the property must reflect the standards for the more restrictive land use. For instance if you are going to be switching from an industrial land use to a residential land use then the property must be classified as a residential property in the RSC and the chemical results entered must be below residential property standards.

Even once a site meets the proper conditions to file an RSC (not contaminated and has evidence to prove it) there is a whole list of other secondary documents that are required to support the RSC submission. These documents include:

- A current legal survey of the RSC property
- A certificate of status for the consultant submitting the RSC (also required for the owner if the owner of the property is a company)
- A letter from the property owner granting the consultant permission to file an RSC in their behalf
- A deed for the property confirming ownership of the property

This list comprises the minimum number of documents you will be asked to submit in support of an RSC submission. The number of document submitted varies from site to site and is governed by the regulation. Owners should be prepared to submit previous reports for the property, chemical results, articles of incorporation and a number of other similar documents.

One final note on the RSC submission process… be prepared for an audit by the MOE. The MOE audits some of the RSCs submitted to ensure the supporting documentation meets the standard. This is different from the initial review of a submitted RSC to ensure the property identification information matches, which may result in the need correct minor inconsistencies like the legal description for the property not matching the one listed on the RSC EXACTLY. Or GPS coordinates for the site not lining up with the Ministry’s data base.

This seems like a good place to stop as it serves as a good segue way into next weeks topic in this thread….the RSC audit process.

Benjamin Goldstein (bgoldstein@aeonegmond.com)

Friday, June 11, 2010

Steps Towards an Record of Site Condition (RSC) – Remediation and Site Cleanup

This weeks Environmental Update post is about site cleanup as it pertains to the RSC submission process. Site cleanup or remediation is the process whereby contaminants at a site are brought within regulatory limits either through chemical, biological or physical processes, or by removal from the site. Remediation only occurs on sites where the Phase II ESA has shown that a chemical species is present above an allowable level at the property. It is important to keep in mind that remediation should only commence once all potential environmental concerns have been addressed. It is very easy for the MOE to reject an RSC submission on the grounds that a thorough search for a potential contaminant of concern has not been properly conducted even at properties where the entire site has been remediated for another contaminant (eg. Though you cleaned the soil of metals did you check for PHCs from the old gas station next door?). Also, prior to commencing a costly remedial option you should always ensure remediation is a viable possibility because site conditions at some properties can make remediation extremely difficult. In cases like these it may be easier to look into a Site Specific Risk Assessment whereby the risk of human/animal exposure to contaminants is calculated and the potential for the offending chemical to migrate from its current location is studied.

At any rate, for sites where remediation is a realistic option there are typically three main options for site cleanup the owner/consultant can choose from:

  1. In Situ Remediation – This is a method of remediation whereby the contamination issue is dealt with on site. For instance, in the case of petroleum hydrocarbon (PHC) contamination in soil, an in-situ option would be to inject colonies of bacteria into the ground which could break down the contamination into a benign product. A parallel situation for groundwater contamination would be the injection of bacteria into the aquifer in order to Though in-situ remediation is typically more expensive and slower than other options, it tends to be less intrusive to day to day activities at the site. Also, some contamination situations necessitate in-situ remediation (eg. When contamination is deep underneath a building, or spread throughout a large groundwater plume.)


     

  2. Ex Situ –Remediation- This option is slightly different from In-Situ as it involves removing the contaminated media from its current location and then performing corrective actions. Paralleling this with the contaminated soil in the above example, an ex-situ remedial option would be to excavate the soil, pile it at another location of the site and douse it in PHC digesting bacteria. In the case of groundwater, pumps could be used to extract the contaminated water to a treatment tank where the water is treated with bacteria or chemicals and then pumped back into the ground once remedial objectives have been met. Though ex-situ remediation is more intrusive to the site, it is often quicker than in-situ as it allows for better contact between the offending chemical and the treatment method, and as the industry saying goes, "remediation is a contact sport". Additionally this method of remediation can lower the costs associated with disposal and backfilling of soil as compared to removal from site.


     

  3. Removal from Site – As you've probably guessed, this is the process of removing contaminated media (typically soil, sometimes sediment) from its original location and replacing it with uncontaminated media. This is typically performed at sites where access to contaminated areas is unhindered and the costs of disposal and excavation are lower than in-situ remediation methods. Removal from site is generally quicker and more cost effective than in-situ but it can rather disruptive to day to day operations at a site (How well will your business operate with fifty dump trucks entering/exiting the property all day and twenty foot deep hole in your parking lot?).

Once the property has been brought within regulatory guidelines the burden of proof now lies on the owner to show to the MOE that the property no longer is contaminated, this done by collecting closure samples. Closure samples are soil or groundwater samples collected at a statistically significant number with respect to the size of the property and/or contaminated area. Where removal from site has been used as a remedial option the number of closure samples is determined by the size of the excavation pit and is governed by the 1996 MOE document, Guidance on Sampling and Analytical Methods for Use at Contaminated Sites in Ontario. For in-situ remediation activities the number of closure samples is different for every site and as such the owner/consultant is responsible for determining the adequate number of closure samples for the site. As a precautionary note, when excavating always wait for clean closure sample results prior to backfilling the excavation pit with new fill, it would be a shame to have to re-excavate your property in order to address leftover contamination.

Lastly, one should keep in mind that a number of best management practices exist to minimize remedial costs and expedite the remediation process, these include; on-site testing to reduce analytical costs and speed up excavations, and soil recycling which can minimize soil disposal fees.

If all goes well, your site will be cleaned and within guidelines and should be ready for the submission of an RSC. Please stop by Environmental Update next week for the continuation in our series about the RSC submission process where we will discuss the actual RSC submission procedure.

Thanks for reading!

Benjamin Goldstein (bgoldstein@aeonegmond.com)

Wednesday, June 2, 2010

Steps Towards a Record of Site Condition (RSC) – The Phase II Environmental Site Assessment (Phase II ESA)

This week’s installment of Environmental Update continues along the same theme which we started last week – outlining the steps towards a Record of Site Condition (RSC). To refresh, last week we spoke of about the Phase I Environmental Site Assessment (ESA) – a study designed to determine the environmental legacy of a property through various record searches, interviews and site visits in order to identify potential environmental risks (contamination) at the site in question.

The Phase II ESA is a continuation of this process whereby the presence of contamination is confirmed or dismissed by means of collecting and testing soil, groundwater and/or sediment samples. Decisions regarding where at the site to collect samples and what chemicals to test for are based areas of concern identified during the Phase I ESA process. Common areas of concerns at sites include but are not limited to:

- areas where dry cleaning operations have occurred
- areas where fuel storage tanks are or were present
- areas were PCB containing materials were used or stored
- areas of a property adjacent to industrial activities
- areas of a property adjacent to or across the street from a gas station
- areas where pesticides or herbicides were potentially used

Once adequate samples have been collected from the site, they are then analyzed for potential contaminants of concern by a certified laboratory. A related best management practice is to utilize on-site testing to reduce laboratory costs and speed up results (more on that later in subsequent Blog entries).

Laboratory results for the samples are compared to applicable criteria (based on land use, environmental factors and water use at the site). If no contamination is found at the site then it is possible to submit an RSC for the site. If contamination is found at a site then further rounds of sampling are usually performed in order to fully understand the scope of the problem. Test results, site maps and geological data are combined in data management programs to delineate the extent, identify sources and speculate the fate of contamination at the site.

Much like the Phase I ESA, the Phase II ESA serves as a guidance document for future activities at the site. The conclusion of the investigation provides the owner with suggested best practices for remediation of the problem, cost estimates for remedial alternatives and rough timelines for remedial activities.

Also like the Phase I ESA, the format for the Phase II ESA has undergone an overhaul under the amendments to O.Reg. 153/04. Major additions to the Phase II ESA process include but are not limited to;

i) Mandatory groundwater sampling at all sites where a Phase II ESA is performed
ii) A list of seventy one (71) potentially contaminating activities at sites that will likely warrant a Phase II ESA before the property can submit an RSC
iii) Mandatory Phase II ESAs for properties that have ever operated as gas stations, automobile repair facilities or dry cleaning facilities

These changes are aimed to bring a level of consistency to the quality of Phase II ESAs being performed and to ensure that all properties are thoroughly investigated prior to proceeding to the RSC submission or the site clean up phase.

Please return to the Blog next week in and check out our next installment in this series – Remediation.

Benjamin Goldstein (bgoldstein@aeonegmond.com)

Tuesday, May 25, 2010

Steps Towards a Record of Site Condition (RSC) – The Phase I Environmental Site Assessment (Phase I ESA)

We start our series of posts about the process of obtaining an RSC for a property with a post on the Phase I ESA. Currently the Phase I ESA is a review of all available information regarding a property in order to develop a complete picture of the environmental legacy of the property. The Phase I ESA as defined by O.Reg. 153/04 includes reviews of a variety of government and private databases (spill records, underground tank records, waste disposal records, etc), aerial photographs, land transfer records, interviews with site occupants and neighbours, as well as a site walkover supervised by a Qualified Person (QP).

The purpose of developing this environmental history of the property in question is to identify if any past or present activities at the site could have resulted in areas of potential environmental concern. From this conclusion the future path towards an RSC is determined. If no areas of potential concern are found then the owner is eligible to submit an RSC. However, if areas of potential concern are found or suspected, then a Phase II ESA and possible remedial work might be warranted at the property. Because the Phase I ESA provides the basis by which the direction of all future work proceeds, it is essential that this phase of the assessment is performed properly. A poor quality Phase I ESA can become a costly mistake down the line during the Ministry of Environments (MOE) RSC review process (more on this in future posts).

The above steps are applicable with the current legislation, but on December 29, 2009, the MOE released Amendment that is set to officially take effect on July 29, 2011(but in AEL’s experience the MOE is already comparing Phase I ESAs to these standards). Major changes to the Phase I ESA process include:

i) Title searches on the property must proceed back to 1850 or until the property was first developed

ii) The QP must have access to ALL areas of the site, barring safety concerns, during the site walkover

iii) All properties that have ever operated as a gas station, automobile repair facility or dry cleaner MUST automatically undergo a Phase II ESA if an RSC is to be submitted

iv) If an owner wishes to change consultants, all work previously performed on the site must be reviewed and signed off by the new consultant

The purpose of these changes is to level the playing field and bring consistency to the quality of Phase I ESA reports that the MOE receives. The changes will also make the Phase I ESA process more time consuming, in-depth and, consequently, more expensive for owners. Lastly, it will be very difficult to change consultants once an investigation on a property has been initiated, meaning that property owners will have to use a high degree of discretion when choosing a consultant to work with.

Remember to visit our blog next week to read the second post in our series about the steps to submitting a RSC - The Phase II Environmental Site Assessment.

Ben Goldstein (bgoldstein@aeonegmond.com)

Tuesday, May 18, 2010

Welcome to our Blog

Hello! All of us here at AEL Environment (formerly Aeon Egmond Ltd) are excited to welcome you to our new BLOG. This endeavour has been initiated by AEL in an effort to provide relevant, up to date, technical information regarding issues related to the environmental site assessment and clean-up. By offering this information in an easy to follow topic based blog format we hope to provide you with easily available and quickly digestible information on various environmental topics.

We also hope to create a forum for discussion on any of the topics which are posted here. This will help us to understand what the market is looking for relative to our service offering and how we can make improvements, so feel free to let us know what you would like to see. We at AEL see this as paramount in fostering interdisciplinary relationships and broadening the scope of discussion. What better way to understand the impact of a topic than having property owners and developers, engineers, lawyers, scientists, planning officials, regulators and other interested parties provide their viewpoints on an issue? Through these types of open discussions we will be able to gain an understanding of the full scope of an issue and as well develop future blog topics to post about. In short….please feel free to reply to any of our blog posts with questions, comments, and suggestions for future topics. Let’s increase collaboration, creativity and understanding in the environmental field!

So now that you have an understanding of our philosophy and vision for this new blog, I will give a brief overview of our company. We are a niche environmental engineering firm focused on site assessment and remediation work. We operate out of two offices in the Greater Toronto Area (west and east) completing projects across Canada. With senior and intermediate level engineers at our disposal, supported by a dedicated team of scientists and field techs, we are able to provide solutions to a variety of engineering problems within our scope of services that include a number of innovative on-site testing and data management tools. Our goal is to provide best site management solutions through a variety of cost and time saving methods. Having completed projects from Phase I Environmental Site Assessments all the way to remediation and site closure, with budgets ranging from as little as a few thousand dollars to over $500,000 , AEL has a proven track record of success in the environmental engineering industry.

So for now, thanks for taking a look at our site. The blog is updated regularly, generally every Tuesday so please check in for a new instalment of Environmental Updates or sign up for our email update service.

Next week we will begin a series of posts on the steps to a Record of Site Condition, from A to Z.